Skip to content

Pressure Vessel Fabrication for Terra Project

Pressure Vessel Fabrication for Terra Project

  • Client: SK Group _ ECOVANCE
  • Duration: 04 months ( November 2024 to February 2025)
  • Location: CNI Factory Nhon Trach_Dong Nai
  • Position: SK’ Vessel Inspector
  • Scope Of Work
    • Review WPS, WPQR, NDE and other related Procedures.
    • Randomly witness and check the work activies at the workshop.
    • Monitor and ensure the project stay on schedule.
    • Updating fabrication progress.
    • Witness/Hold Point in ITP as: material receiving inspection, cutting, fit up, welding, blasting, coating, mechanical assembly, hydraulic assembly, functional test, factory acceptance test, mechanical completion.
    • Review NDT procedures to ensure compliance with the client’s specifications, codes, and standards.
    • Witness mockup test and demo NDT methods of all the NDT contractors involved as per client’s procedures.
    • Ensure the filing & record keeping of the Project.
    • Make a weekly report to the Site Manager.
    • Monitoring through fabrication to ensure production meets project requirements.
    • Follow up NCR if any non-compliance observed.
    • Report to the Owner on rate of progress and quality.